Contract Bid Abstract

SAP 028-599-086 - SAP 028-599-086, Bridge 28J45 Rooster Valley, Blackhammer TwpVan Gundy Excavating ICON Constructors, LLC Zenke, Inc 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLUMP SUM0.4$2,000.00$800.00$1,000.00$400.00$8,000.00$3,200.00
2021.501MOBILIZATIONLUMP SUM0.6$2,000.00$1,200.00$1,000.00$600.00$8,000.00$4,800.00
2101.511CLEARING & GRUBBINGLUMP SUM1$2,500.00$2,500.00$1,000.00$1,000.00$8,000.00$8,000.00
2104.501REMOVE FENCELIN FT340$2.00$680.00$1.00$340.00$3.00$1,020.00
2105.501COMMON EXCAVATION (P)CU YD1,300$7.50$9,750.00$6.00$7,800.00$8.00$10,400.00
2105.522SELECT GRANULAR BORROW (CV) (P)CU YD90$25.00$2,250.00$22.00$1,980.00$21.00$1,890.00
2118.501AGGREGATE SURFACING CLASS 5TON530$15.00$7,950.00$16.00$8,480.00$15.50$8,215.00
2211.501AGGREGATE BASE CLASS 5 MODTON580$15.00$8,700.00$16.00$9,280.00$15.50$8,990.00
2411.511STRUCTURE EXCAVATION CLASS U (P)CU YD360$6.00$2,160.00$10.00$3,600.00$8.00$2,880.00
2412.51110X5 PRECAST CONCRETE BOX CULVERTLIN FT40$750.00$30,000.00$640.00$25,600.00$760.00$30,400.00
2412.51210X5 PRECAST CONCRETE BOX CULV END SECTEACH2$8,500.00$17,000.00$8,000.00$16,000.00$8,000.00$16,000.00
2442.501REMOVE EXISTING BRIDGELUMP SUM1$2,500.00$2,500.00$9,000.00$9,000.00$4,000.00$4,000.00
2451.509AGGREGATE BEDDING (CV) (P)CU YD82$25.00$2,050.00$30.00$2,460.00$24.00$1,968.00
2501.51112" CS PIPE CULVERTLIN FT33$35.00$1,155.00$35.00$1,155.00$29.50$973.50
2501.51512" CS PIPE APRONEACH2$100.00$200.00$300.00$600.00$173.00$346.00
2511.501RANDOM RIPRAP CLASS VCU YD90$35.00$3,150.00$45.00$4,050.00$42.00$3,780.00
2563.601TRAFFIC CONTROLLUMP SUM0.4$1,000.00$400.00$1,000.00$400.00$1,500.00$600.00
2563.601TRAFFIC CONTROLLUMP SUM0.6$1,000.00$600.00$1,000.00$600.00$1,500.00$900.00
2573.502SILT FENCE, TYPE MSLIN FT1,035$2.50$2,587.50$2.40$2,484.00$3.00$3,105.00
2574.508FERTILIZER TYPE 2POUND75$2.05$153.75$2.05$153.75$1.00$75.00
2575.501SEEDINGACRE0.3$1,950.00$585.00$1,950.00$585.00$400.00$120.00
2575.502SEED MIXTURE 25-141POUND20$7.60$152.00$7.60$152.00$4.00$80.00
2575.515MULCH MATERIAL TYPE 4ACRE0.2$2,250.00$450.00$2,250.00$450.00$2,000.00$400.00
2575.523EROSION CONTROL BLANKETS CATEGORY 3SQ YD410$1.75$717.50$1.75$717.50$2.50$1,025.00
2575.572RAPID STABILIZATION METHOD 4SQ YD350$2.75$962.50$2.75$962.50$2.00$700.00
 Totals for project SAP 028-599-086 $98,653.25 $98,849.75 $113,867.50
 
Contract Total:$98,653.25$98,849.75$113,867.50