The browser you are using is not supported. Please use a current version of Firefox, Chrome, Edge, Safari, or Opera.
Bid Abstract
SAP 028-599-078 - SAP 028-599-078 Remove Bridge No L4560 & Road Obliteration | Generation X Construction LLC | ICON Constructors, LLC | Zenke, Inc | The Mathiowetz Construction Company | Phoenix Corp | Pember Companies, Inc | Van Gundy Excavating | LinnCo, Inc |
Item No. | Item | Units | Quantity | Unit Price | Total Price | Unit Price | Total Price | Unit Price | Total Price | Unit Price | Total Price | Unit Price | Total Price | Unit Price | Total Price | Unit Price | Total Price | Unit Price | Total Price |
2021.501 | MOBILIZATION | LS | 1 | $7,000.00 | $7,000.00 | $7,500.00 | $7,500.00 | $22,000.00 | $22,000.00 | $38,220.00 | $38,220.00 | $10,000.00 | $10,000.00 | $18,880.00 | $18,880.00 | $30,000.00 | $30,000.00 | $19,140.00 | $19,140.00 |
2104.503 | REMOVE METAL CULVERT | L F | 20 | $20.00 | $400.00 | $10.00 | $200.00 | $15.00 | $300.00 | $7.00 | $140.00 | $10.00 | $200.00 | $20.00 | $400.00 | $10.00 | $200.00 | $42.00 | $840.00 |
2104.504 | REMOVE CONCRETE PAVEMENT | S Y | 3,225 | $9.00 | $29,025.00 | $12.00 | $38,700.00 | $8.70 | $28,057.50 | $17.00 | $54,825.00 | $10.00 | $32,250.00 | $18.00 | $58,050.00 | $16.00 | $51,600.00 | $19.14 | $61,726.50 |
2104.507 | REMOVE AGGREGATE | C Y | 614 | $10.00 | $6,140.00 | $6.00 | $3,684.00 | $9.00 | $5,526.00 | $8.50 | $5,219.00 | $10.00 | $6,140.00 | $19.00 | $11,666.00 | $10.00 | $6,140.00 | $10.00 | $6,140.00 |
2104.607 | SALVAGE ROCK | C Y | 21 | $15.00 | $315.00 | $25.00 | $525.00 | $9.00 | $189.00 | $20.00 | $420.00 | $60.00 | $1,260.00 | $19.00 | $399.00 | $10.00 | $210.00 | $42.00 | $882.00 |
2105.603 | MINOR GRADING | L F | 2,270 | $7.00 | $15,890.00 | $2.50 | $5,675.00 | $4.00 | $9,080.00 | $2.10 | $4,767.00 | $10.00 | $22,700.00 | $5.00 | $11,350.00 | $5.00 | $11,350.00 | $1.50 | $3,405.00 |
2211.607 | AGGREGATE BASE FROM STOCKPILE | C Y | 21 | $10.00 | $210.00 | $15.00 | $315.00 | $20.00 | $420.00 | $20.00 | $420.00 | $60.00 | $1,260.00 | $30.00 | $630.00 | $10.00 | $210.00 | $15.00 | $315.00 |
2442.501 | REMOVE EXISTING BRIDGE | LS | 1 | $18,000.00 | $18,000.00 | $35,000.00 | $35,000.00 | $45,000.00 | $45,000.00 | $16,254.00 | $16,254.00 | $55,000.00 | $55,000.00 | $26,000.00 | $26,000.00 | $50,000.00 | $50,000.00 | $78,500.00 | $78,500.00 |
2501.502 | 15" GS PIPE APRON | EACH | 2 | $500.00 | $1,000.00 | $300.00 | $600.00 | $220.00 | $440.00 | $153.00 | $306.00 | $500.00 | $1,000.00 | $240.00 | $480.00 | $250.00 | $500.00 | $385.50 | $771.00 |
2501.503 | 15" CS PIPE CULVERT | L F | 40 | $30.00 | $1,200.00 | $50.00 | $2,000.00 | $39.00 | $1,560.00 | $33.00 | $1,320.00 | $30.00 | $1,200.00 | $40.00 | $1,600.00 | $30.00 | $1,200.00 | $21.50 | $860.00 |
2575.501 | TURF ESTABLISHMENT | LS | 1 | $5,000.00 | $5,000.00 | $2,500.00 | $2,500.00 | $6,900.00 | $6,900.00 | $14,900.00 | $14,900.00 | $6,000.00 | $6,000.00 | $11,000.00 | $11,000.00 | $7,500.00 | $7,500.00 | $5,397.00 | $5,397.00 |
| Totals for project SAP 028-599-078 | | $84,180.00 | | $96,699.00 | | $119,472.50 | | $136,791.00 | | $137,010.00 | | $140,455.00 | | $158,910.00 | | $177,976.50 |
|
Contract Total: | $84,180.00 | $96,699.00 | $119,472.50 | $136,791.00 | $137,010.00 | $140,455.00 | $158,910.00 | $177,976.50 |